September 2019
Project Kick off
January 2020
System Requirements Review (SRR) - DESY, Elop, IAI
March 2020
Camera System Design Review (SDR) - DESY
April 2020
Payload System Design Review (SDR) - Elop
May 2020
Spacecraft System Design Review (SDR) - IAI
October 2020
Payload Perliminary Design Review (PDR) - Elop
December 2020
Camera Perliminary Design Review (PDR) - DESY
February 2021
Spacecraft Perliminary Design Review (PDR) - IAI
October 2021
Camera Critical Desgin Review (CDR) - DESY
January 2022
Payload Critical Design Review (CDR) - Elop
April 2022
Spacecraft Critical Design Review (CDR) - IAI
May 2023
Ground Control Segment Critical Design Review (GCS CDR) - IAI
We are here!
January 2026
Supply of Camera - DESY
October 2026
Supply of Payload - Elop
November 2026
Ground Control Segment (GCS) Readiness Review
march 2027
Science Operation Center (SOC) Readiness Review
October 2027
ULTRASAT Delivery Review Board (DRB) - IAI
Q4 2027
launch